BEP, MIDP and TIDP: Planning Information Delivery That Survives the Tender

A BIM Execution Plan is often written to win the tender and then abandoned, so delivery improvises and handover disappoints. This guide explains what the BEP, the task information delivery plans (TIDP) and the master information delivery plan (MIDP) each do, and how to keep them useful through delivery.

What the BEP states

The BEP states how a delivery team will meet the appointing party's information requirements: who does what, to what standard, in what environment and on what schedule. ISO 19650-2 expects a pre-appointment BEP with the tender and a confirmed BEP after award. Together with the TIDPs and the MIDP, it plans who delivers what, and when.

How the TIDP and MIDP fit together

Plan fieldTypical content
Container ID and titleThe information container following the project naming convention
Author and reviewerWho produces the container and who checks it
Level of information needThe agreed need for that container at that milestone
StatusThe CDE state and suitability, for example WIP or Shared
Milestone and due dateThe information exchange the container supports

Ten steps to a BEP

  1. Information requirements: capture OIR, AIR, PIR and EIR, and set exchange requirements and acceptance criteria.
  2. BIM use selection: choose high-value uses and avoid unnecessary model effort.
  3. Delivery team structure: assign roles and the responsibility matrix.
  4. CDE workflow set-up: the Work in Progress, Shared, Published and Archive states and the status codes.
  5. Level of information need: geometry, data and documentation by purpose.
  6. openBIM exchange rules: IFC, BCF, IDS and COBie, with software-neutral workflows.
  7. Model production method: authoring standards, naming, classification and templates.
  8. Coordination and issues: the clash process, issue ownership and close-out.
  9. Information delivery plan: a TIDP per task team and the MIDP, with milestones.
  10. Asset handover readiness: asset data, O&M information and digital-twin foundations.

Keep the BEP alive

The BEP should be updated as the project moves between phases, not written once for the tender. A useful test is traceability: every EIR requirement should be answered by a step in the BEP, and each step should map to a dated milestone in the TIDP and MIDP.

What to check

This guide is drawn from DEIM's approved knowledge base. The ten steps align with the ISO 19650-2 delivery process; the way of working described is DEIM's recommended approach.

References

Related service: Digital Delivery (BIM and ISO 19650)

Related guides

Talk to DEIM

If you would like a second pair of eyes on your information requirements, plan or coordination process, write to us.

DEIM provides decision-support and document-assistance tools, not legal advice. Legal outputs require review by qualified counsel. Each client's licensed standards and contracts are used isolated within their own project.
DEIM provides decision-support and document-assistance tools, not legal advice. Legal outputs require review by qualified counsel. Each client's licensed standards and contracts are used isolated within their own project.